Specification Changes & Flexible Adjustments

Specification Changes & Flexible Adjustments

Finding after sampling that a cable length needs adjusting, a wiring sequence has to change, or even a connector part number needs replacing is common during development. SyncTronics assesses the real impact based on when the change is raised, works first on returning or reallocating existing material, and reissues the drawing for confirmation, keeping disruption to the project as low as possible.

One point to be clear about upfront: the earlier a change is raised, the more room there is to handle it. The actual impact depends on how far material purchasing and production have progressed.

When Changes Usually Arise

The period after the first sample build and before pilot production starts is where changes concentrate. It is also the best time for them, since material has generally not been committed in volume.

Changes raised during pilot production are less common but still happen. In those cases the approach has to be assessed against production progress.

What Gets Changed Most Often

Cable length. The most frequent and the most straightforward. As long as material has not been cut, the adjustment has almost no knock-on effect.

Wiring sequence. Second most common, usually driven by circuit revisions on the design side. Once changed, we build exactly to the specified wiring sequence.

Connector part number. The most troublesome of the three. When it changes after an order is placed, connectors already purchased may no longer be usable and need separate handling.

How Each Stage Is Handled

Timing of change

Actual impact

How it is handled

Material not yet purchased

Almost none

Specification and drawing updated directly

Material received, production not started

Material may sit idle

Return or exchange negotiated with the supplier first; alternatively, complete the current batch with existing material

Production partially complete

Completed units cannot be changed

Production paused, completed and remaining quantities counted, handling of completed units discussed

Complete and awaiting shipment

Rework required

Product recalled and rework feasibility assessed, such as removing connectors and rebuilding

One practical limit on rework deserves attention. Removing a connector and re-crimping shortens the cable slightly. If the original design carries a tight length tolerance, the reworked product may no longer meet the specification, and we confirm and flag this in advance. Some cables and custom connectors cannot be disassembled for rework at all, and those cases have to be assessed separately.

How Existing Material Is Handled

Material is handled in a set order of priority, with the aim of limiting your loss as far as possible:

  1. Return to the supplier
  2. Exchange with the supplier for the parts the revised specification requires
  3. Complete the current batch with the original part number, introducing the change from the next batch
  4. Reallocate to another project, including other customers or industry partners
  5. Remaining material taken over by the customer

The first four all avoid material becoming dead stock. Only when none of those routes works does the fifth apply, and that is discussed with you in advance.

Drawings Require Re-approval

Every specification change requires a reissued drawing and fresh approval, regardless of how small the change is.

The reason is that the drawing serves as the basis for two things at once: our shipping standard and your acceptance standard. If it is not updated in step, the two sides end up judging conformance differently. A 5mm length adjustment and a connector replacement follow the same process.

Lead Time Impact

There is no fixed answer, as it depends on the stage at which the change arises.

A practical way to estimate is to treat the revised work as a fresh build and then add or subtract roughly a week. Where disassembly and rework are needed, it can take longer than building new. Where the change is a specification adjustment before production starts, the impact is comparatively limited.

Where Changes Cannot Be Accommodated

When a product is already complete and involves cables or custom connectors that cannot be disassembled for rework, the change is not technically feasible. Material for these products is usually specific enough that it cannot readily be used elsewhere.

In these cases our recommendation is to use the current batch as built, and introduce the new design from the following batch. This avoids wasting material already committed and gives the revised specification a full window for confirmation and verification.

Information Worth Providing With a Change Request

  • The specific items changing and the new specification
  • Original drawing number or part number
  • Reason for the change, which helps identify whether other options exist
  • Whether the current batch should change as well, or the change starts from the next batch
  • Any delivery constraints

Related Products & Technical Resources

If you are currently arranging prototype builds, adjusting specifications, or coordinating delivery, the following may help:

High-Mix Low-Volume Project Support | NPI & MOQ | SyncTronics Technology

Multi-Item Low-Volume Prototyping | Shared Materials, Quotation Methods & Lead Times | SyncTronics Technology

Delivery Coordination & Scheduling | Production Planning, Early Release & Delay Management | SyncTronics Technology

Drawing & Specification Review | Approval Drawings, Pin Definition & Tolerance Confirmation | SyncTronics Technology

Wire Harness Assembly | Custom Wire Harness & Cable Assembly | SyncTronics Technology

Need to Adjust a Confirmed Specification?

Send us the items changing and the new specification. SyncTronics will first confirm where material and production currently stand, assess the workable approach and lead time impact, then reissue the drawing for your approval.

Need Wire Harnesses, Connectors, Electromechanical Components, or Custom Solutions? Contact Us Today

Whether you are looking for connectors, cables, wire harness assemblies, electromechanical components, or complete electronic interconnect solutions, SyncTronics provides professional technical support and engineering evaluation for product selection, specification verification, New Product Introduction (NPI), OEM/ODM customization, as well as high-speed transmission, high-reliability, and other specialized application requirements.

We welcome you to visit our Contact Us page and share your project requirements and contact information. Our team is committed to responding quickly and professionally, evaluating the most suitable products and electronic interconnect solutions based on your product specifications, application requirements, and project objectives. We also provide technical recommendations and customized engineering support to help shorten product selection and development time, reduce project risks, and accelerate your path to mass production. We look forward to the opportunity to work with you and provide reliable technical support and practical solutions for every stage of your project.